DrawingHow long it takes
Median19 months
IssuedFebruary 2026
Sheet04 of 21

Seventeen to twenty seven months. The median is nineteen.

From the first meeting to the day you unlock the door. Two thirds of that is spent before a single truck arrives, which is the part nobody expects and the part that decides everything afterwards.

The three phases
4 to 7Months, design and engineering
8 to 16Weeks, permitting
11 to 16Months, construction
17 to 27Months, first meeting to keys

The fast end and the slow end are both real houses.

Four months of design plus two of permitting plus eleven of construction is seventeen, and that is a well drawn house of moderate size on a clean lot in a fast jurisdiction. Seven plus four plus sixteen is twenty seven, and that is a big house on a difficult site in a town that reviews trees before it reviews buildings.

Nineteen is the median of the last twelve. It is not the fast end, and we would rather quote you the middle than the number that makes the meeting go well.

Size drives construction more than anything else. The Butler Chain house is 6,720 square feet and took nineteen months of construction alone. The New Broad house is 3,310 and took twelve.

Permitting is not the same everywhere
JurisdictionPermit clockWhat makes it that way
Winter Park12 to 16 weeksTree review and design review both run before building review opens the file
City of Orlando10 to 14 weeksStraightforward, and slower in the two months after a storm season
Orange County, unincorporated8 to 11 weeksThe fastest jurisdiction we build in
Windermere and the lakefront10 to 14 weeksPlus a dock permit on a separate clock, about seven months
Lake Nona10 to 14 weeksAfter 4 to 10 weeks of community architectural review, which comes first
Measured from the day the engineer seals the set to the day the permit is issued, on our own jobs since 2023.
The last twelve houses

Nine of the last twelve finished on or before the date in the contract.

Below is every house we have handed over in the last three years, plotted against its own contract completion date. The vertical line is that date. The mark is the day the family got the keys. Three of them landed past the line, and each of those three carries its reason underneath it.

Weeks against the contract date
6 early3Contract date369 late
Via TuscanyWinter Park, 2024
Butler ChainWindermere, 2023
Laureate ParkLake Nona, 2025
New BroadBaldwin Park, 2025
Osceola CourtWinter Park, 2024

Late by seven weeks. A named storm in the framing window, seven days of stand down, two truss packages replaced

Down PointWindermere, 2024
Chase RoadWinter Park, 2023
Meeting PlaceBaldwin Park, 2024

Late by five weeks. Custom steel windows nine weeks past their promised date, four weeks absorbed by resequencing

Lake Sue AvenueWinter Park, 2025
Wyndham BayWindermere, 2025
Northlake ParkLake Nona, 2024

Late by six weeks. Kitchen redrawn in month ten at the owner's request, plumbing moved in a slab already poured

Bryn MawrWinter Park, 2023
Keys handed over on or before the date Keys handed over after the date The date written in the contract

Nine of the last twelve finished on or before the date in the contract. Here are the three that did not, and why.

Questions

Three questions about the calendar.

Can you go faster if I pay more?

Not meaningfully, and the places where money does buy time are small. Expedited plan review saves two or three weeks in some jurisdictions. Paying to expedite a window order occasionally works. What money cannot compress is concrete curing, inspection sequencing, or the fact that a house has to be dried in before the inside of it can begin. Builders who promise a fast schedule usually deliver it by starting construction on drawings that are not finished, and then the redraw happens on your site instead of on paper.

When does the clock actually start?

We date the contract schedule from permit issue rather than from the first meeting, because everything before permit involves an architect, an engineer and a municipality rather than us. But we tell you both numbers, and the one to plan your life around is the seventeen to twenty seven months from the first meeting. If a builder quotes you eleven months, ask him what he is measuring from.

What is the longest a Castellano house has taken?

Thirty four months, finished in 2019. A large house on a lakefront lot where the soil report was wrong. We found muck at four feet across a third of the footprint, and the foundation was redesigned and repermitted while everything stopped. The family knew within eleven days of the discovery what it would cost and what it would take. It is the worst schedule we have ever run and we still put a plate on it.

Closing

Two hundred and fourteen plates.
We know where all of them are.

Four to six houses a year, on purpose. Tell us where the lot is, or tell us you are still looking, and we will say honestly whether we are the right company for it. If we are not, we will tell you who is.

Read by Miguel Castellano, usually the same day